Square Yards Calculator

Twelve feet times 18 feet is 216 square feet, which is 24.00 square yards. Add a 10 percent waste factor and the order becomes 26.40 square yards. At 4 inches deep the same area needs 2.67 cubic yards of concrete, soil or mulch, and 2.93 with waste.

Enter length and width to get square yards, square feet and square meters, add a waste factor, and turn depth into cubic yards of soil, mulch or concrete.

By the Lelifi editors ·

Key takeaways

A 12 by 18 foot patio, drawn as 3 by 3 foot squares0 ft6 ft12 ft18 ft12 ft6 ft0 ft24 squares of 9 sq ft each216 sq ft / 9 = 24.00 sq yd216 sq ft = 20.07 sq m216 sq ft at 4 in = 2.67 cu ydat 10 percent waste: 26.40 sq ydEach square is one square yard, so the count of squares is the square yardage.Six columns of 3 ft make the 18 ft side; four rows make the 12 ft side.Order 26.40 sq yd of material and the cuts come out of the slack.
A 12 by 18 foot patio drawn as twenty four 3 by 3 foot squares, each one a square yard, with the conversion and depth figures beside it.
One cubic yard spread out, by depth1 in2 in3 in4 in324 sq ft162 sq ft108 sq ft81 sq ftA cubic yard is 27 cubic feet, so area covered equals 324 divided by the depth in inches.216 sq ft at 4 in deep needs 216 x 4 / 324 = 2.67 cu yd; with 10 percent waste, 2.93 cu yd.Depth figures match the USDA NRCS mulch coverage chart, which lists 108 sq ft per yard at 3 in.
One cubic yard spread at 1, 2, 3 and 4 inches covers 324, 162, 108 and 81 square feet, the depth rule that turns square yards into cubic yards.
On this page
  1. What a square yard is, and the exact number behind it
  2. Measure length and width, then multiply
  3. Square yards, square feet, square meters and acres
  4. Materials that get sold by the square yard
  5. From square yards to cubic yards when you add a depth
  6. How much to buy: the waste factor
  7. Measuring mistakes that cost money
  8. A patio job from tape measure to delivery

What a square yard is, and the exact number behind it

A square yard is a square with sides one yard long, and one yard is 3 feet, so the area works out to 3 x 3 = 9 square feet. In inches that is 36 x 36 = 1,296 square inches. The yard itself is pinned to the metric system: the NIST Handbook 44, Appendix B defines 1 yard as exactly 0.9144 meter, a definition set in 1959, which makes one square yard equal to 0.83612736 square meters.

The NIST Guide to the SI, Appendix B.9 lists the same square yard factor as 8.361 274 E-01 square meters and the cubic yard as 7.645 549 E-01 cubic meters. Those two factors cover most of what a yard-based project needs, because area comes from squaring a length and volume comes from cubing it.

Three conversions run this page:

The 324 in the last line is 9 x 12 x 3, the number of square feet one cubic yard covers at a single inch of depth. Divide 324 by the depth and you get the coverage of one yard of any loose material: 324 sq ft at 1 inch, 162 at 2 inches, 108 at 3 inches, 81 at 4 inches. The FHWA unit conversion table rounds the square yard to 0.836 square meters, the same factor to three decimals.

Measure length and width, then multiply

For a rectangle, the whole job is one multiplication. A patio 12 feet by 18 feet is 12 x 18 = 216 square feet, and 216 / 9 = 24.00 square yards. The same patio is 20.07 square meters, and if you measured it as 4 yards by 6 yards, the answer is the same 24.00 square yards, because 4 x 6 = 24 and the yard is already the unit you want.

Two measurements in different units are the common slip. A 12 foot 6 inch side is 12.5 feet, not 12.6, because 6 inches is half a foot. Enter 12.5 and 18 into the calculator above and you get 25.00 square yards instead of 24.00, a difference of one square yard, which at carpet prices is real money.

ShapeHow to measureArea formula12 by 18 foot example
RectangleBoth sides, same unitlength x width216 sq ft = 24.00 sq yd
SquareOne sideside x side14.7 ft per side gives 24.00 sq yd
CircleDiameter3.1416 x (d / 2) squared16.6 ft across gives about 24 sq yd
TriangleBase and heightbase x height / 218 ft base, 24 ft height gives 216 sq ft
L shapeTwo rectanglesAdd both areasSplit into 12 x 14 plus 12 x 4

An L shaped yard splits into rectangles that you add together. A larger example: a driveway 30 feet by 40 feet is 1,200 square feet, or 133.33 square yards, and 111.48 square meters. Compare that with a 15 by 20 foot room, which is 300 square feet, 33.33 square yards, and 27.87 square meters. Both figures come straight out of the calculator above with the measurements in feet.

Square yards, square feet, square meters and acres

Different sellers quote different units for the same patch of ground, and the price per unit changes with the unit. Here is the ladder, with a few landmarks on it.

UnitSquare feetSquare yardsSquare metersTypical use
1 square yard910.83612736Carpet, sod, concrete
10 square yards90108.36A walk-in closet floor
50 square yards4505041.81One pallet of sod
100 square yards90010083.61A two-car garage floor
500 square yards4,500500418.06A large lawn
1 acre43,5604,8404,046.86A housing lot

The acre sits at 4,840 square yards because it is 43,560 square feet and 43,560 / 9 = 4,840. A square mile holds 3,097,600 square yards, which is 640 acres. Going the other way, 100 square yards is a bit under 84 square meters, so a metric quote of 84 square meters describes about the same floor as 100.46 square yards.

Costs convert the same way, and this is where people get burned. A carpet quoted at $6.50 per square yard costs $0.72 per square foot, because 6.50 / 9 = 0.7222. A quote of $6.50 per square foot describes a floor nine times as expensive. Check the unit on the price tag before you check the price.

Materials that get sold by the square yard

Three materials in particular get quoted in square yards, and each one has its own habit of measuring.

Sod. The Purdue Extension guide to establishing a lawn from sod notes that vendors typically sell sod by the square yard, that one pallet holds about 50 square yards, or 450 square feet, and that you should order about 10 percent more than the measured area to cover cutting and fitting. Mississippi State Extension puts pallets in the same 450 to 500 square foot range and suggests roughly 5 percent extra for a straightforward yard. Purdue also figures sod at 35 to 40 pounds per square yard, so a 24.00 square yard lawn weighs roughly 840 to 960 pounds on the pallet.

Carpet. Carpet comes on rolls 12 feet wide, which is 4 yards, and one linear yard of that roll covers 12 square feet. A 12 by 18 foot room therefore takes 6 linear yards of the roll, and 6 x 4 = 24.00 square yards. A 15 by 20 foot room is 33.33 square yards on the floor, and because the roll is only 12 feet wide the leftover strip along the 15 foot side is waste you pay for anyway.

Concrete. State highway departments price sidewalk and driveway work by area. The Alabama DOT standard specifications list concrete sidewalk and driveway pay items per square yard, with the accepted area computed in square yards. Ready mix, on the other hand, is sold by the cubic yard, which is where the depth calculation in the next section comes in.

MaterialSold inA 24.00 sq yd job needs
Sodsquare yards, pallets of 501 pallet, with slack left over
Carpetsquare yards26.40 sq yd at 10 percent waste
Concretecubic yards2.67 cu yd at 4 inches deep
Mulchcubic yards1.33 cu yd at 2 inches deep

From square yards to cubic yards when you add a depth

Area tells you how much ground you cover. Depth tells you how much material fills it, and depth is measured in inches while material is sold in cubic yards. One cubic yard is 27 cubic feet, and spread an inch deep it covers 324 square feet, so the cubic yards you need are:

cubic yards = square feet x depth in inches / 324

For the 216 square foot patio at 4 inches of concrete, that is 216 x 4 / 324 = 2.67 cubic yards. Add a 10 percent waste factor and the order becomes 2.93 cubic yards. The driveway example runs the same way: 1,200 square feet at 3 inches is 1,200 x 3 / 324 = 11.11 cubic yards, and 11.67 cubic yards with 5 percent waste.

Depth1 cubic yard coversMaterial it suits
1 inch324 sq ftSand bedding under pavers
2 inches162 sq ftMulch, the USDA rule of thumb
3 inches108 sq ftGravel paths, fine mulch maximum
4 inches81 sq ftConcrete slabs, coarse bark
6 inches54 sq ftTopsoil for new turf

The USDA NRCS mulching guide calls a 2 inch depth of organic mulch the rule of thumb for holding moisture and keeping weeds down, with finely textured shredded hardwood capped at 3 inches and coarse pine bark nuggets allowed up to 4 inches. The same guide prints a coverage chart that lists 162 square feet per cubic yard at 2 inches and 108 at 3 inches, which matches the 324 formula to the digit.

For the patio bed that means 216 square feet at 2 inches needs 216 / 162 = 1.33 cubic yards of mulch. At 4 inches, the coarse bark maximum, it needs 216 / 81 = 2.67 cubic yards, the same figure as the concrete slab because the depth matches.

How much to buy: the waste factor

Measured area is the floor of the order, not the order. Cuts around edges, overlaps at seams and the piece that tears during handling all come out of the same delivery, so every trade adds a waste percentage before ordering. The calculator above applies your waste factor to both the square yards and the cubic yards, and prices the order on the waste-adjusted figure.

JobTypical wasteWhy
Rectangular lawn, straight edges5 percentRolls cut clean, little trimming
Sod around beds and curves10 percentPurdue recommends about 10 percent more
Carpet in a rectangular room10 percentRoll direction and seams
Concrete slab5 to 10 percentUneven subgrade, spillage, over excavation
Mulch on open beds0 to 5 percentNo cuts, spread thickness adjusts

Worked on the patio numbers: 24.00 square yards at 10 percent waste is 26.40 square yards to order. At a carpet price of $6.50 per square yard that comes to $171.60, and at $18.50 per square yard the same 26.40 square yards runs $488.40. The 33.33 square yard room at $22.00 per square yard, with the same 10 percent, prices at $806.67. Each price comes from the waste-adjusted quantity, which is what the invoice will say.

Suppliers round on their side too. Ready mix concrete sells in quarter yard steps, sod sells by the whole pallet, and carpet retailers charge for the full linear yard of the roll. Round up to the unit your supplier sells in, and let the waste factor absorb the remainder rather than trying to buy a partial pallet.

Measuring mistakes that cost money

Most bad yardage orders trace back to one of five habits, and all five are cheap to avoid.

One check catches most of them: multiply the two measurements, divide by 9, and see whether the result is close to the number of 3 foot paces you would take across the space. A patio you cross in 4 paces by 6 paces should land near 24.00 square yards, and a number far from that means a unit slipped somewhere.

For big areas, break the plot into rectangles, calculate each one, and add them. A yard with a house, beds and a driveway subtracts, so measure the grass area rather than the lot: the Purdue sod guide figures turf area by taking the lot, removing the house footprint, and working from what is left.

A patio job from tape measure to delivery

Here is the whole workflow on one set of numbers, the 12 by 18 foot patio, using the calculator above at each step.

Step one, measure. Both sides in feet: 12 and 18. Area is 216.00 square feet.

Step two, square yards. 216 / 9 = 24.00 square yards, which is 20.07 square meters if the supplier quotes metric.

Step three, depth. A 4 inch concrete slab needs 216 x 4 / 324 = 2.67 cubic yards. The same area as a 2 inch mulch bed needs 1.33 cubic yards, and as a 3 inch gravel path it needs 2.00 cubic yards.

Step four, waste. Ten percent on the area gives 26.40 square yards to order, and on the concrete it gives 2.93 cubic yards. Order 3.0 cubic yards from the ready mix plant, since quarter yard steps run up from 2.93.

Step five, price. At $6.50 per square yard the 26.40 square yards invoice at $171.60. Per square foot that is $0.72, and per square meter about $7.77, because 26.40 square yards is 22.08 square meters and 171.60 divided by 22.08 gives that figure.

StepFigureUnit
Measured area216.00sq ft
Area in yards24.00sq yd
Area in meters20.07sq m
Concrete at 4 in2.67cu yd
Order with waste26.40sq yd
Concrete order2.93cu yd
Cost at $6.50$171.60dollars

The same five steps work for a lawn, a gravel path or a bed of topsoil. Only the depth and the unit the supplier sells in change, and the calculator above keeps the arithmetic in one place.

Frequently asked questions

How many square feet are in a square yard?

Nine. A square yard is a 3 by 3 foot square, so 3 x 3 = 9 square feet. Divide square feet by 9 to get square yards, and 216 square feet becomes 24.00 square yards.

How do I calculate square yards from feet?

Multiply length by width in feet to get square feet, then divide by 9. A room 12 feet by 18 feet is 216 square feet, which is 24.00 square yards.

How many square yards is a 12 by 12 room?

144 square feet, which is 16.00 square yards. With a 10 percent waste factor the order becomes 17.60 square yards of carpet or sod.

How many square feet is a pallet of sod?

About 450 square feet, or 50 square yards, per the Purdue Extension sod guide. Suppliers stack pallets between 450 and 500 square feet, so confirm with your farm before ordering.

How much is a square yard in square meters?

Exactly 0.83612736 square meters, because a yard is 0.9144 meters and 0.9144 squared is that number. A 24.00 square yard patio is 20.07 square meters.

How many cubic yards do I need for a 4 inch slab?

Multiply square feet by 4 and divide by 324. A 216 square foot slab needs 2.67 cubic yards, and with a 10 percent waste factor 2.93 cubic yards, so order 3.0 from the plant.

How many square yards is an acre?

Exactly 4,840. An acre is 43,560 square feet and 43,560 divided by 9 gives 4,840 square yards, which is also about 4,046.86 square meters.

How much does one cubic yard of mulch cover?

162 square feet at 2 inches deep, 108 square feet at 3 inches, and 81 square feet at 4 inches, per the USDA NRCS coverage chart. The 324 formula gives the same figures.

How deep should mulch be?

The USDA NRCS guide calls 2 inches the rule of thumb for organic mulch, caps shredded hardwood at 3 inches, and allows coarse pine bark up to 4 inches. Deeper layers can suffocate roots.

How much does 1 cubic yard of concrete cover at 3 inches?

108 square feet, which is 12 square yards. A 1,200 square foot driveway at 3 inches needs 1,200 x 3 / 324 = 11.11 cubic yards, or 11.67 with 5 percent waste.

How much waste should I add for sod?

Purdue Extension suggests about 10 percent more sod than the measured area to cover cutting and fitting, and Mississippi State Extension suggests roughly 5 percent for a simple rectangular yard.

How heavy is a square yard of sod?

Purdue figures sod at 35 to 40 pounds per square yard, so a 50 square yard pallet weighs about 1,750 to 2,000 pounds. Plan the delivery spot accordingly.

How do I convert a price per square foot to a price per square yard?

Multiply by 9. A carpet at $0.72 per square foot is $6.50 per square yard, and the same carpet at $22.00 per square yard is $2.44 per square foot.

Why is concrete sold in cubic yards but priced per square yard?

Ready mix is volume, so the plant sells cubic yards. Contractors quote the finished slab by area, so the price per square yard assumes a stated thickness and converts depth on paper.