A 20 by 16 foot slab on an 18 inch grid needs about 480 feet of No. 4 rebar, which is 321 pounds of steel. That is 24 sticks of 20 foot bar, or 27 with a 10 percent waste allowance, bought one bar per grid line each way with a 20 inch lap at every splice.

Enter your slab size, grid spacing and bar size to get the number of bars, total feet, sticks to buy, lap allowance and weight in pounds.

By the Lelifi editors ·

Key takeaways

Counting bars on an 18 in grid, 20 x 16 ft slabBars along length = 16 ft x 12 = 192 in / 18 in = 10.67 -> 11 + 1 = 12 barsBars along width = 20 ft x 12 = 240 in / 18 in = 13.33 -> 14 + 1 = 15 barsLength direction = 12 bars x 20 ft = 240 ftWidth direction = 15 bars x 16 ft = 240 ft= 480 ft of No. 4 rebarRound every fraction up, then add the closing bar at each edge.
The grid-count math for a 20 by 16 foot slab on an 18 inch grid.
A typical $194 order for the 20 x 16 ft patio slab$162$24No. 4 bars, 27 sticks at $6.00 ($162)Wire ties and chairs ($24)Cutting wheel wear ($8)
Where the money goes on a typical patio slab order.
On this page
  1. How the bar count works: one bar per grid line
  2. Worked example: a 20 by 16 foot patio slab
  3. Bar sizes, diameters and weight per foot
  4. Lap splices: why long runs need extra length
  5. Weight, cost and what to budget
  6. Chairs, edge distance and the rest of the mat
  7. Common mistakes when ordering rebar

How the bar count works: one bar per grid line

Rebar in a slab forms a grid, and the count starts from one simple idea: you need one bar for every grid line in each direction. If your slab is 16 feet wide and your bars sit 18 inches apart, then 192 inches of width divided by 18 inches per space gives you 10.67 spaces. Round up to 11 spaces, add the closing bar at the far edge, and you need 12 bars running that direction.

The same arithmetic runs the other way, and then the two counts multiply out into total length:

Always round the space count up, never down, and never forget the closing bar. Every calculator for rebar uses this same grid rule, including the one at the top of this page, so you can check any layout in a few seconds.

Worked example: a 20 by 16 foot patio slab

Say you are pouring a 20 foot by 16 foot patio, 4 inches thick, with No. 4 bar on an 18 inch grid. That is one of the most common residential layouts, and it shows every step of the estimate.

The weight comes from the pounds-per-foot figure for No. 4 bar. At 0.668 pounds per foot, the slab needs 480 x 0.668 = 320.64 pounds of steel. With the waste allowance it is 528 x 0.668 = 352.70 pounds. Those two numbers, feet and pounds, are what a steel supplier quotes against, so write both down before you call.

The figure below shows the same grid-count arithmetic laid out line by line.

Bar sizes, diameters and weight per foot

Rebar sizes are numbered in eighths of an inch, so a No. 4 bar is 4/8 of an inch across, which is half an inch. The bar number also drives the lap splice length, the chair spacing and, most importantly for your order, the weight. The weights below follow the standard bar tables published under ASTM A615, the specification that covers the deformed bars sold at every lumber yard.

Bar sizeDiameterWeight per foot20 ft stick weightCommon use
No. 3 (3/8 in)0.375 in0.376 lb7.52 lbWalkways, footings, ties
No. 4 (1/2 in)0.500 in0.668 lb13.36 lbPatios, driveways, slabs
No. 5 (5/8 in)0.625 in1.043 lb20.86 lbHeavy drives, grade beams

You can sanity-check any bar by its weight: a No. 4 stick is 20 x 0.668 = 13.36 pounds. When a supplier quotes by the ton, divide your total pounds by 2,000 to compare quotes fairly. The Concrete Reinforcing Steel Institute publishes the full table for larger bar numbers, but the three above cover almost every residential slab.

Lap splices: why long runs need extra length

Bars come in 20 foot sticks, so any run longer than 20 feet needs a splice. The standard overlap is 40 bar diameters, which the Concrete Reinforcing Steel Institute treats as the common residential splice and which your local code may exceed. The two bars sit side by side inside the concrete, wired together, so tension passes from one bar into the concrete and back into the next.

Each splice adds one lap to the run, so a 30 foot No. 4 run is a 20 ft stick plus a 10 ft cut, with one 20 inch overlap, giving 31.67 feet of bar per finished run. On the 20 foot patio runs above, no splice is needed, which is why the worked example stays clean at 480 feet. If your slab is longer than 20 feet in either direction, add one lap for every joint and let the calculator at the top of this page do the rounding for you.

Weight, cost and what to budget

Feet and pounds both matter when you buy. Retail yards price by the 20 foot stick, typically 5 to 8 dollars for No. 4 depending on region and steel prices. Steel suppliers quote by weight, and the pounds figure is also what you need to plan delivery, because a pallet of rebar gets heavy fast.

Slab size, No. 4 at 18 in gridBarsTotal feetWeightSticks with 10% waste
10 x 10 ft8 + 8160 ft106.88 lb9
12 x 12 ft9 + 9216 ft144.29 lb12
20 x 16 ft12 + 15480 ft320.64 lb27
24 x 24 ft17 + 17816 ft545.09 lb45
30 x 24 ft17 + 211,014 ft677.35 lb56

For the patio example, a typical order looks like the breakdown below: 27 sticks at 6 dollars each is 162 dollars, plus ties and chairs. Note that two of the slabs in the table run past 20 feet in one direction, so their real orders include the lap feet discussed above. The calculator adds laps automatically.

The figure below breaks that typical order down by line item.

Chairs, edge distance and the rest of the mat

Rebar does no good lying on the dirt. Concrete protects steel from rust only when the bar is fully surrounded, so the mat has to sit in the middle of the pour. Three small details handle that:

Chairs run a few dollars per hundred, and a five gallon bucket of tie wire lasts most homeowners years. The steel in a 20 by 16 foot slab weighs 320.64 pounds, which is more than one person should carry in a single trip, so plan on moving sticks to the pour site in batches before you start.

Common mistakes when ordering rebar

Most rebar estimates go wrong in the same few ways, and all of them are easy to catch before you load the truck.

MistakeWhat happensHow to avoid it
Rounding grid spaces downThe last bar lands past the slab edge or spacing drifts wideAlways round up: 10.67 spaces is 12 bars, not 11
Forgetting the closing barThe far edge has no steel in itCount is spaces + 1 in every direction
Skipping laps on long runsRuns cannot reach, and you burn a second tripAdd 40 bar diameters per splice on runs over 20 ft
Ordering zero wasteOffcuts and bent bars leave you short mid-pourAdd about 10 percent to the total feet

One more habit worth stealing from contractors: write the final cut list on the slab plan before ordering. Knowing that the width direction needs 15 bars at 16 feet each tells you instantly that every 20 foot stick leaves a 4 foot offcut, and offcuts are exactly what you use for the little hooks and dowels every pour seems to need.

Frequently asked questions

How much rebar do I need for a 20x20 slab?

At an 18 inch grid with No. 4 bar you get 15 bars running each way. Each 20 ft run needs one stick, so the slab takes about 600 feet of bar, which is 30 sticks and roughly 401 pounds of steel before waste.

How many pounds is a 20 foot stick of #4 rebar?

A 20 foot stick of No. 4 weighs 13.36 pounds, because the bar weighs 0.668 pounds per foot. A No. 3 stick of the same length is 7.52 pounds and a No. 5 stick is 20.86 pounds.

What spacing should I use for a patio slab?

An 18 inch grid is the common choice for a 4 inch residential patio or walkway, and 24 inches works for light-duty slabs on firm soil. Driveways usually drop to 12 or 18 inches because of vehicle loads.

What does 40 bar diameters mean for a lap splice?

It means the overlap length is 40 times the bar diameter. A No. 4 bar is half an inch across, so two bars overlap 20 inches. A No. 5 bar overlaps 25 inches and a No. 3 bar overlaps 15 inches.

How much does rebar cost per stick?

At big-box stores a 20 foot stick of No. 4 usually runs 5 to 8 dollars, No. 3 a little less and No. 5 a little more. Our example slab works out to about 162 dollars in bars at 6 dollars a stick before ties and chairs.

Can I use wire mesh instead of rebar?

For thin 4 inch slabs on decent soil, welded wire mesh is a common substitute. Rebar handles heavier loads and holds cracked concrete together better, which is why driveways often use rebar while garden paths use mesh.

How far should rebar be from the edge of the slab?

Keep the outer bars about 2 to 3 inches in from the formed edge. That keeps steel covered with concrete on all sides, which protects it from rust and keeps the slab corners from chipping.

Do I need rebar at all for a 4 inch slab?

For a small shed pad or walkway, not always. A 4 inch slab on well compacted soil with control joints can go unreinforced, but rebar is cheap insurance for driveways, patios that carry hot tubs, and any slab over poor soil.

Why does 10 percent waste matter when ordering?

Cuts leave short offcuts, some bars arrive bent, and layouts rarely land on even stick lengths. Adding 10 percent turns the 480 feet in our example into 528 feet, which is why the calculator shows 27 sticks instead of 24.

What size rebar should I use in a driveway?

No. 4 bar at an 18 inch grid is the common residential driveway choice, stepping up to No. 5 for heavy trucks or soft ground. No. 3 is too light for wheel loads and is better saved for footings and ties.

How do I keep the rebar in the middle of the slab?

Set the mat on chairs, which are small supports that hold the bar about 2 inches up from the subbase. Space chairs every 2 to 3 feet along the bars so the grid does not sag when you walk on it while pouring.

Is rebar sold by the stick or by weight?

Retail yards sell it by the 20 foot stick, while steel suppliers quote by the ton or by weight per foot. That is why the calculator shows both: the stick count tells you what to buy, and the weight tells you what to expect on a supplier quote.