Sand Calculator
A 12 by 20 foot paver base 1 inch deep needs 20 cubic feet, or 0.74 cubic yards, of bedding sand. That is 2,200 lb of damp sand at 110 lb per cubic foot, or 2,420 lb and 1.21 tons with a 10 percent waste margin, which takes 49 bags.
Area to fill
Sand and order
| Sand to order | |
| Area | |
| Volume before waste | |
| Volume with waste | |
| Weight | |
| Tons | |
| Bags | |
| Coverage from one ton | |
| Coverage from one bag | |
| Bulk cost at your price per ton |
Volumes are loose, so the waste margin covers uneven subgrade and spillage. Density follows the condition you pick: dry loose 100 lb per cu ft, damp 110, wet and compacted 120. Coverage rows assume the depth you entered and ignore waste. One cubic yard is 27 cubic feet. Everything runs in your browser and nothing is uploaded.
Measure the space and the depth, pick dry or damp sand, and see cubic yards, tons, bags and cost before you order, with a waste allowance built in.
Key takeaways
- Bedding sand volume = area x depth / 12 in cubic feet; divide by 27 for cubic yards
- Dry sand runs 100 lb per cu ft, 2,700 lb per cu yd; wet compacted sand reaches 120 lb per cu ft
- A 12 by 20 foot pad at 1 inch takes 22 cu ft with waste: 1.21 tons of damp sand, 49 fifty-pound bags
- One ton of dry sand covers 240 sq ft at 1 inch, 120 sq ft at 2 inches, 60 sq ft at 4 inches
- One cubic yard of dry sand is 54 fifty-pound bags, so bulk beats bags past 20 or 30 bags
On this page
- What this sand calculator takes and returns
- Volume comes first: length x width x depth
- Dry, damp and compacted sand do not weigh the same
- Tons, cubic yards and 50 lb bags
- Paver base: the 1 inch bedding layer
- Sandboxes, lawns and mortar beds
- What moves the number: moisture, waste and dust
- A worked order, start to finish
What this sand calculator takes and returns
The calculator asks for three measurements and three order details. The measurements are the length and width of the area in feet and the depth of sand in inches. The order details are the sand condition, a waste allowance and the bag size you will buy. Press Calculate sand and the results table fills in the area, the volume in cubic feet and cubic yards, the weight in pounds and tons, the number of bags, how far one ton and one bag go at your depth, and the cost at your price per ton.
Sand comes in more grades than people expect, and each job has its own. Concrete sand is coarse and washed, masonry sand is fine and screens smooth, and play sand is washed and rounded for sandboxes. This page covers the quantity math that all of them share. If you are filling a children's sandbox with play sand at a set depth, the sandbox sand calculator walks through the depth standards in detail, and the polymeric sand calculator handles the sand swept into paver joints, which is priced by the pound of joint volume rather than by depth over an area.
Volume comes first: length x width x depth
Every sand order starts as a volume, and the volume is the footprint times the depth. Work in feet and inches, then divide the depth by 12 so the units match. For a 12 by 20 foot paver pad at 1 inch: 240 x 1 / 12 = 20 cubic feet, and 20 / 27 = 0.74 cubic yards. One cubic yard is 27 cubic feet, because a yard measures 3 feet on every side and 3 x 3 x 3 = 27.
Odd shapes do not need a surveyor. Split the area into rectangles, work each one out, and add the volumes. A circle uses 3.14 x r x r for the area, close enough that the waste margin absorbs the difference. L-shaped patios are two rectangles minus nothing, as long as the rectangles do not overlap.
Volume is the number to get right before weight enters the picture. Subgrades are rarely flat, so a pad specified at 1 inch deep has low spots that eat 2 inches and high spots that eat none. Sand also settles after rain and traffic. The waste allowance in the calculator exists for both reasons, and 10 percent is the default for a reason: it covers an uneven subgrade without doubling the order.
Dry, damp and compacted sand do not weigh the same
Volume tells you the hole. Weight tells you the truck, and the two are connected by density, which swings more for sand than for almost any other landscaping material. Dry, loose sand runs about 100 lb per cubic foot, which is 2,700 lb per cubic yard. Damp sand carries water between the grains and runs around 110 lb per cubic foot. Sand that is wet and compacted, the state it reaches under a plate compactor or after a week of rain, can reach 120 lb per cubic foot. The USGS tracks construction sand and gravel as a mineral commodity in its annual Mineral Commodity Summaries report, and material yards quote weights in the same dry-to-wet range.
What the condition does to a cubic yard:
| Condition | lb per cu ft | lb per cu yd | tons per cu yd | kg per cu m |
|---|---|---|---|---|
| Dry, loose | 100 | 2,700 | 1.35 | 1,600 |
| Damp | 110 | 2,970 | 1.49 | 1,760 |
| Wet, compacted | 120 | 3,240 | 1.62 | 1,920 |
Notice what this means in practice: the same 0.74 cubic yard hole holds anywhere from about 2,000 lb to 2,400 lb of sand depending on the day. If your supplier sells by the ton, the condition you pick changes the bill by about 20 percent. If the supplier sells by the yard, the condition changes the weight on your driveway, which matters when you are shoveling it or when a delivery truck parks on soft ground.
Tons, cubic yards and 50 lb bags
Suppliers sell sand three ways: by the cubic yard for bulk deliveries, by the ton at some yards and quarries, and by the 50 lb bag at retail. The conversions between them are fixed once you fix the density. With dry sand at 100 lb per cubic foot, one ton is 20 cubic feet, one cubic yard weighs 2,700 lb, and 2,700 / 50 = 54 fifty-pound bags per cubic yard.
Coverage is the same math read backwards. One ton of dry sand is 20 cubic feet, so spread over an area it reaches 20 x 12 = 240 square feet at 1 inch deep, and half that at 2 inches. Here is the coverage table for dry sand:
| Depth | Sq ft per cu yd | Sq ft per ton | 50 lb bags per 100 sq ft |
|---|---|---|---|
| 1 in | 324 | 240 | 16.7, so buy 17 |
| 2 in | 162 | 120 | 33.3, so buy 34 |
| 3 in | 108 | 80 | 50 |
| 4 in | 81 | 60 | 66.7, so buy 67 |
A single 50 lb bag holds about 0.5 cubic feet of dry sand, which covers 6 square feet at 1 inch or 3 square feet at 2 inches. That is enough to see why bagged sand suits patch jobs and mortar beds, and why anything over 20 bags is usually cheaper in bulk even after delivery fees.
Paver base: the 1 inch bedding layer
The most common sand order is the bedding layer under pavers. The stack is compacted gravel below, then a 1 inch layer of coarse concrete sand, screeded flat and never compacted, then the pavers themselves. The 1 inch figure matters in both directions: a thinner bed starves the low corners of the paver, and a thicker bed lets pavers sink under foot traffic, which is why installers screed with 1 inch pipes as rails and lay the pavers directly on the loose sand.
Work the bedding layer with the calculator by measuring the paved area and entering 1 inch of depth. A 12 by 20 foot patio, 240 square feet, takes 20 cubic feet or about 0.74 cubic yards before waste. The bedding sand is damp when it comes from the yard, so the calculator's 110 lb per cubic foot setting matches what the delivery weighs.
Two neighbors on this site cover the rest of the stack. The gravel calculator sizes the compacted base below the sand, and the polymeric sand calculator sizes the joint sand swept into the paver gaps afterwards. Bedding sand and joint sand are different products: bedding sand stays loose, while polymeric sand contains binders and sets after watering, so they are never interchangeable even though both are called sand.
Sandboxes, lawns and mortar beds
Depth is a design decision that changes with the job, and it is worth writing down before you measure:
| Project | Typical depth | What the depth does |
|---|---|---|
| Paver bedding layer | 1 in, screeded | Levels the pavers over the gravel base |
| Children's sandbox | 6 in in a 12 in box | Half fill leaves room to play and keeps sand in |
| Lawn topdressing | 0.25 in | Smooths the surface without smothering grass |
| Leveling low spots | 0.5 in per pass | Deep fills need several passes and raking in |
| Mortar bed under tile | 0.375 to 0.5 in | Bonds the tile to the substrate |
| Under above-ground pools | 2 in, masonry sand | Cushions and protects the liner |
A worked sandbox: a 5 by 5 foot box filled to 6 inches needs 5 x 5 x 0.5 = 12.5 cubic feet, which is 1,250 lb of dry sand or 25 fifty-pound bags. Play sand is the right grade here; construction sand can carry dust and sharp particles.
A worked mortar bed: 100 square feet of floor at 0.375 inch is 100 x 0.375 / 12 = 3.13 cubic feet. At 100 lb per cubic foot that is about 313 lb, or 6.25 bags, so buy 7. Mortar beds use masonry sand mixed with cement, roughly 1 part cement to 3 or 4 parts sand by volume.
What moves the number: moisture, waste and dust
Moisture is the first mover. Water fills the gaps between grains without adding volume, so a damp pile weighs 10 percent more than a dry one and a soaked pile up to 20 percent more, while covering exactly the same area. This is why sand is sold by volume at most yards: weight would charge you for last week's rain.
Waste is the second mover. Sand falls off shovels, sticks to wheelbarrows, disappears into low spots and spreads past the forms. The 10 percent default in the calculator matches what installers order for a reasonably flat pad; for sand going onto soft soil, or for a first job, 15 percent is more honest than 10.
Dust is the third thing to plan for, and it is a health question, not a tidy-up question. Sand and stone dust contain crystalline silica, and breathing the fine fraction causes silicosis. The OSHA silica standard for construction requires wet methods and dust controls when cutting or sweeping silica-bearing materials, and the rule itself sits in 29 CFR 1926 Subpart Z. Damp the pile before moving it and avoid dry sweeping the patio when the job is done.
A worked order, start to finish
Put the whole chain together for the 12 by 20 foot paver pad at 1 inch, buying damp sand with a 10 percent waste margin:
| Step | Calculation | Result |
|---|---|---|
| Area | 12 x 20 | 240 sq ft |
| Volume | 240 x 1 / 12 | 20 cu ft |
| With 10 percent waste | 20 x 1.1 | 22 cu ft, 0.81 cu yd |
| Weight, damp at 110 | 20 x 110 x 1.1 | 2,420 lb |
| Tons | 2,420 / 2,000 | 1.21 tons |
| Bags of 50 lb | 2,420 / 50 | 48.4, so 49 bags |
| Bulk cost at $45 per ton | 1.21 x 45 | $54.45 |
| Bag cost at $6 per bag | 49 x 6 | $294 |
The last two rows are the argument for bulk. The same sand costs five times as much by the bag once you pass a couple of dozen bags, and that gap pays for a delivery fee several times over. Bags still win for small mortar beds, sandbox top-ups and jobs with no truck access. If the order needs other stone, the concrete calculator and the mulch calculator use the same area-times-depth starting point for their own materials.
Frequently asked questions
How much does a cubic yard of sand weigh?
Dry, loose sand weighs about 2,700 lb per cubic yard, or 1.35 tons. Damp sand runs about 2,970 lb and wet, compacted sand can reach 3,240 lb per cubic yard, a swing of about 20 percent on the same volume.
How many 50 lb bags of sand make a cubic yard?
A cubic yard of dry sand weighs 2,700 lb, and 2,700 / 50 = 54 bags. Damp sand at 110 lb per cubic foot would take 59 or 60 bags to fill the same yard.
How many square feet does a ton of sand cover at 1 inch?
One ton of dry sand is 20 cubic feet, which covers 240 square feet at 1 inch deep. The same ton covers 120 square feet at 2 inches and 80 square feet at 3 inches.
How much sand do I need for a 12x20 paver patio?
At the standard 1 inch bedding depth, a 12 by 20 foot patio takes 20 cubic feet, or 0.74 cubic yards. In damp sand with a 10 percent waste margin that is about 2,420 lb, 1.21 tons or 49 fifty-pound bags.
How deep should paver bedding sand be?
1 inch after screeding. Installers screed the loose sand down to 1 inch using pipes as rails. Deeper beds let pavers rock and settle under traffic, and the bedding layer is never compacted before the pavers go on.
How much sand do I need for a 5x5 sandbox?
At the usual 6 inch fill depth for a 12 inch deep box: 5 x 5 x 0.5 = 12.5 cubic feet, which is 1,250 lb of dry sand or 25 fifty-pound bags of play sand.
How much area does one 50 lb bag of sand cover?
A 50 lb bag is about 0.5 cubic feet of dry sand. Spread at 1 inch it covers 6 square feet; at 2 inches it covers 3 square feet. Bags suit patch jobs and mortar beds, not whole patios.
How much sand does a mortar bed need for 100 sq ft of tile?
At a 0.375 inch bed, 100 x 0.375 / 12 = 3.13 cubic feet, about 313 lb of dry sand. That is 6.25 fifty-pound bags, so buy 7. Mix masonry sand with cement at roughly 1 to 3 or 1 to 4 by volume.
Does wet sand weigh more than dry sand?
Yes, and the water adds nothing to coverage. Damp sand runs about 110 lb per cubic foot against 100 for dry, and wet, compacted sand reaches 120 lb per cubic foot. That is why suppliers sell by the cubic yard rather than by weight.
How do I convert cubic feet of sand to cubic yards?
Divide by 27. One yard is 3 feet on each side, so a cubic yard holds 3 x 3 x 3 = 27 cubic feet. Twenty cubic feet of bedding sand is 20 / 27 = 0.74 cubic yards.
How much does sand cost per ton and per bag?
Bulk sand commonly runs roughly $15 to $50 per ton depending on grade and region, plus delivery. Bagged play sand and masonry sand typically run $5 to $7 per 50 lb bag, which is $200 to $280 per ton. Bulk wins past 20 or 30 bags.
Why order 10 percent more sand than the volume?
Subgrades are uneven, so a nominally 1 inch layer runs deeper in the low spots, and sand sticks to tools, spills in transit and settles after rain. Ten percent covers a flat pad; soft or rough ground deserves 15 percent.
Is sand dust dangerous to breathe?
Sand contains crystalline silica, and respirable silica dust causes silicosis. Dampen the pile before moving it, avoid dry sweeping, and follow wet cutting and dust control practices required by OSHA's construction silica standard.
How many tons of sand fit in a dump truck?
A common single axle delivery truck hauls 5 to 10 tons per load, and sand yards usually have a delivery minimum of 1 to 3 tons. Check the truck's rated capacity with the supplier; wet sand at 1.62 tons per cubic yard fills a truck faster than you would expect.
Spotted a wrong number or a broken result?
More Home Improvement tools
- ADU Cost Calculator
- Acreage Calculator
- Aggregate Cost Calculator
- Air Conditioner Room Size & BTU Calculator
- Aluminum Fence Cost Calculator
- Asphalt Calculator
- Awning Cost Calculator
- Bathtub vs Shower Footprint Calculator
- Bleach Dilution Calculator
- Block Mortar Calculator
- Board Footage Calculator
- Board and Batten Layout Calculator
- Board and Batten Siding Calculator
- Board on Board Fence Calculator
- Borax Ant Killer Calculator
- Brick Calculator
Fee schedules, rates and rules change without notice. Always confirm important figures with the official source before you rely on them.